Influence of project characteristics, regulatory pathways, and environmental complexity on hydropower licensing timelines in the US
Pracheil B.M.; Levine A.L.; Curtis T.L.; Aldrovandi M.S.P.; Uría-Martínez R.; Johnson M.M.; Welch T.
发表日期2022
ISSN0301-4215
卷号162
英文摘要In the U.S., hydropower is expected to play an important role in supporting a zero-carbon energy transition so it's becoming increasingly important the hydropower regulatory process provides robust environmental and other protections while maintaining regulatory efficiency. In this study, we created a dataset of project and license characteristics and milestones using hydropower licensing documents from 107 randomly selected projects to 1) quantify the length of steps in the licensing timeline and 2) quantitatively identify factors associated with licensing timeline length and sources of uncertainty. We found original licenses had shorter average timelines than relicenses and project capacity was only related to timeline length when license type (i.e., original, relicense) was included in analyses. Both licensing timeline length and variability were impacted by the licensing process (Alternative, Integrated, Traditional) used. Projects with greater environmental complexity (e.g., endangered species) had significantly longer timelines than projects that were less environmentally complex. We attributed shorter timelines for original licenses to lower environmental complexity (e.g., no endangered species) because most original licenses involved development of already impacted sites. Projects with greater environmental complexity significantly impact resources that may require greater stakeholder involvement and increased study that can lead to longer licensing timelines. © 2022 The Authors
语种英语
scopus关键词Hydroelectric power; Carbon energy; Endangered species; Energy transitions; Environmental complexity; Licensing process; Project characteristics; Regulatory pathway; Regulatory process; Sources of uncertainty; Zero carbons; Conservation; energy policy; environmental effect; project management; quantitative analysis; regulatory approach; regulatory framework; stakeholder; United States
来源期刊Energy Policy
文献类型期刊论文
条目标识符http://gcip.llas.ac.cn/handle/2XKMVOVA/256360
作者单位Environmental Sciences Division, Oak Ridge National Laboratory, Oak Ridge, TN 37831, United States; Strategic Energy Analysis Center, National Renewable Energy Laboratory, Golden, CO 80401, United States; Water Power Technologies Office, Department of Energy, Washington, D.C 20585, United States
推荐引用方式
GB/T 7714
Pracheil B.M.,Levine A.L.,Curtis T.L.,et al. Influence of project characteristics, regulatory pathways, and environmental complexity on hydropower licensing timelines in the US[J],2022,162.
APA Pracheil B.M..,Levine A.L..,Curtis T.L..,Aldrovandi M.S.P..,Uría-Martínez R..,...&Welch T..(2022).Influence of project characteristics, regulatory pathways, and environmental complexity on hydropower licensing timelines in the US.Energy Policy,162.
MLA Pracheil B.M.,et al."Influence of project characteristics, regulatory pathways, and environmental complexity on hydropower licensing timelines in the US".Energy Policy 162(2022).
条目包含的文件
条目无相关文件。
个性服务
推荐该条目
保存到收藏夹
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Pracheil B.M.]的文章
[Levine A.L.]的文章
[Curtis T.L.]的文章
百度学术
百度学术中相似的文章
[Pracheil B.M.]的文章
[Levine A.L.]的文章
[Curtis T.L.]的文章
必应学术
必应学术中相似的文章
[Pracheil B.M.]的文章
[Levine A.L.]的文章
[Curtis T.L.]的文章
相关权益政策
暂无数据
收藏/分享

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。